Highway 20 Drainage Improvement
blank space

For Immediate Release:  Friday, August 2, 2013

Contact: Adam McMahon, 605-892-2872

 

Highway 20 Drainage Improvement

 

CAMP CROOK, S.D. – The South Dakota Department of Transportation will begin a drainage improvement project on Highway 20 in Harding County on Monday, Aug. 5.

 

Highway 20 in Camp Crook will be closed for 0.2 miles to through traffic during a portion of the project and traffic will be detoured on 1st Street South and Miller Street.

 

Motorists can expect up to 15 minute delays, loose gravel, shoulder drop offs and equipment crossing or entering the highway.

 

The prime contractor on the $133,000 project is Sacrison Paving, Inc. of Whitewood and the completion date is Sept. 1.

 

For more information, contact Adam McMahon with the Department of Transportation at 605-892-2872.

 

Complete road construction information can be found at www.safetravelusa.com/sd or by dialing 511.

 

- 30 -