ABERDEEN, S.D. – The South Dakota Department of Transportation has begun the intersection modification work to add left turn lanes on Highway 281 and 142nd Street at the Warner exit south of Aberdeen. 

 

Intersection modification work to add left turn lanes will also be done at Highway 281 and 130th Street north of Wylie Park in Aberdeen.

 

The intersection modification operations will reduce traffic to one lane. Speed limits thru the construction zones will be 45 mph.

 

This work is part of a nearly $758,000 contract with Lien Transportation Co. to do work on Highway 281 in the Aberdeen region.

 

The expected completion date for the intersection modifications is July 31, with an overall completion date of Sept. 15.

 

For complete road construction information, visit www.safetravelusa.com/sd or call 511.

 

 