Asphalt Concrete Resurfacing & Guardrail Work
blank space

For Immediate Release:  Friday June 1, 2018

Contact: Harry Johnston, 605-394-1639 

 

DEADWOOD, S.D. – Crews will begin micro-milling work on the resurfacing project south of Deadwood on Highway 385 the week of June 4, 2018.

 

Work on the project involves milling of the road surface, asphalt paving, pipe work on the shoulder, replacement of the guardrail, signing and pavement marking work. The 6.4-mile project begins 1.3 miles north of Nemo Road and ends at the Highway 385/85 junction at Pluma.

 

Work on the project is scheduled to be completed by mid-October 2018.

 

The prime contractor on this $2.3 million project is Bituminous Paving, Inc. of Ortonville, Minnesota.

 

For complete road construction information, visit www.safetravelusa.com/sd or dial 511.

 

 