Road Work to Resume on Burr Street in Mitchell
blank space

For Immediate Release:  Thursday, April 4, 2019

Contact: Rick Brandner, 605-995-8120

 

MITCHELL, S.D. – The South Dakota Department of Transportation is scheduled to resume construction work on Burr Street from Walmart to McDonalds on Monday, April 8.

 

The work remaining includes median concrete, curb and gutter, sidewalk, landscaping, lighting and pavement markings.

 

Beginning on April 8, the passing lanes in each direction will be closed while crews complete work in the median. Access to businesses will remain open.

 

This is the last year of work on the project which began in 2017.  The project completion date is June 15, 2019.

 

T & R Contracting from Sioux Falls is the prime contractor on the $16 million project.

 

For complete road construction information visit www.safetravelusa.com/sd or dial 511.

 

-- 30 --

 