Reconstruction of I-29 North of Sisseton to Begin
blank space

For Immediate Release:  Thursday, May 2, 2019

Contact:  Matt Brey, 605-882-5166

 

 

WATERTOWN, S.D. – The South Dakota Department of Transportation says a project to reconstruct Interstate 29 from just north of Sisseton to the North Dakota border will begin in the southbound lanes on Tuesday, May 7, depending on weather.

 

Traffic will be placed in a two-way configuration in the northbound lanes with a reduced speed limit to 65 mph and a 12-foot width restriction.

 

Work on the project includes overlaying the existing pavement and improving bridge decks and guardrails.

 

The prime contractor on this $17 million project is Reede Construction of Aberdeen and is scheduled to be complete by November.

 

For complete road construction information, visit www.safetravelusa.com or dial 511.

 

 