Work To Begin on Bridge Over Interstate 90 at Exit 112
blank space

For Immediate Release:  Thursday, May 30, 2019

Contact:  Brenda Flottmeyer, 605.394.1638

 

RAPID CITY, S.D. – The South Dakota Department of Transportation says bridge repair work will begin on the Interstate 90 eastbound onramp bridge one mile east of Wall on June 1.

 

Work includes concrete milling, bridge deck repairs and low slump concrete overlay to extend the service life of the bridge. Work is scheduled to be completed by June 30.

 

Access to eastbound I-90 from Highway 14A will be closed. Traffic will be detoured to Exit 109 one mile west of Wall. 

 

The overall completion date of this project is Oct. 18, 2019. 

 

PCIRoads, LLC. of St. Michael, Minnesota is the prime contractor on this $1.7 million project.

 

For complete road construction information, visit www.safetravelusa.com/sd or dial 511.

 

 