U.S. Highway 385 Pavement Repairs
Posted: Thursday, September 29, 2011
For Immediate Release: Thursday, September 29, 2011
Contact: Bryan Parks, 605-394-1640
U.S. Highway 385 Pavement Repairs
Deadwood, S.D. – The South Dakota Department of Transportation will be reducing traffic on U.S. Highway 385, south of Deadwood, to one lane beginning Tuesday, October 4, so crews can perform pavement repair work.
The closures will take place between the hours of 7 a.m. and 7 p.m. Traffic will be guided through the area by flaggers and delays up to 10 minutes can be expected. Two-way traffic will be restored during non-working hours. Travelers should allow extra travel time until the work is complete.
Work is scheduled to be completed by Friday, October 7.
Sacrison Paving Inc. of Whitewood is the contractor on the $323,000 project.
For more information, contact Bryan Parks with the Department of Transportation at (605)394-1640.
--30--