Burr Street Mitchell Reconstruction Project

Phase 2 - 2018: Interim completion date is November 16, 2018

Traffic Control and Access During Construction

  • Maintenance of at least one lane of traffic in each direction including provisions for left and right-hand turns.
  • Maintenance of access to homes and businesses.
  • Minimizing the slope of temporary ramps between existing pavement and new pavement that traffic must cross at intersections and business accesses. Due to the elevation changes between the existing and the proposed pavement, ramp lengths of 25-feet or more may be required.
  • Maintain drainage of existing and new facilities.
  • Provide for pedestrian traffic as appropriate to the area where work is being performed.
  • Traffic Patterns maps for April 2018 to June 2018